Plaza Update

The carpet in the Large Print area of the Plaza has been laid and it looks great!  They have also installed the ceiling.  Next up is the installation of the glass in the new windows and the shelving for the Large Print collection.  After the tile work is complete in the main hallway they will lay the tile in this area.  After that we will be able to move the Large Print collection back into the the Plaza and this section will be ready to open.  It should be ready to open in early March.