This is the library’s Technology Plan through 2020. What will you find here? Major technology-related projects, with an explanation of why we’re doing it and the goals for the project; A timeline and timeframe for the project to start; how much the project costs and where the funds are coming from; if the project is connected to another project; and the project team.
Dates and timeframes are usually an estimate, so those will change! Also – If something’s missing, let us know.
2016
Scheduling Software
- Goal: Install and rollout of scheduling software
- Why: Provide centralized and easy-to-use scheduling software.
- Timeframe: 2015 – 2016
- Budget: Already purchased
- Project Priority: Standalone project
- Project Team: Rob Banks
Gigabit for community project
- Goal: Help community gigabit team when needed
- Why: Gina is leading community meetings on becoming a gigabit city. She will need ongoing technology consultations and support to make this happen.
- Timeframe: 2015-2016
- Budget: N/A
- Project Priority: Standalone project
- Project Team: Gina, Shelly Buhler, Digital Services
Teen Spaces remodel Planning
- Goal: Choose technology components for teen spaces remodel
- Why: The Edge and David J’s areas of the library are being remodeled, and will have technology needs.
- Timeframe: 2015-2016
- Budget: TBD
- Project Priority: Standalone project
- Project Team: Youth Services, Digital Services, Facilities
Circulation Lobby redesign
- Goal: Help plan technology needs for this project
- Why: The main floor redesign project with include technology, and Digital Services needs to help plan for those needs.
- Timeframe: 2015-2016
- Budget: TBD
- Project Priority: Standalone project
- Project Team: New Service Model team, Digital Services
Bibliocommons Project
- Goal: Install Bibliocommons.
- Why: Improve customer access to the library’s resources.
- Timeframe: January – May 2016
- Project Priority: Standalone project
- Project Team: Digital Services, Technical Services
Tween tablet Expansion Project
- Goal: Purchase five tablets, storage and charging station for YA desk.
- Why: This is an expansion of the two-iPad pilot project.
- Timeframe: 2016
- Budget: Can come from Kids Library project money
- Project Priority: connected to the teen space redesigns
- Project Team: Digital Services, Youth Services
Public Website Improvements
- Goal: Continue ongoing list of improvements to public website
- Why: Continue improving the website.
- Timeframe: ongoing
- Budget: N/A
- Project Priority: Standalone project
- Project Team: Digital Services, Creative Group
Kids Library Website
- Goal: Redesign the Kids Library website including sections for kids, teens, and parents.
- Why: We need a Kids Library and a teens website that represents everything we do in those areas.
- Timeframe: 2016
- Budget: N/A
- Project Priority: Standalone project
- Project Team: Digital Services, Marketing, Youth Services
Evaluate EMS
- Goal: Evaluate EMS and other calendar/event management products to see what other options are available.
- Why: We have used EMS for almost 10 years – it’s time to re-evaluate to make sure we use the best tool for the library.
- Timeframe: July-September 2016
- Budget: N/A
- Project Priority: Standalone project
- Project Team: Digital Services, Event Resources, Marketing
Customer iPads/tablets/laptop checkout
- Goal: Evaluate need for tablets and laptops for customer checkout.
- Why: Customers have requested tablets, and they provide a mobile and fun digital experience while in our building.
- Timeframe: 2016
- Budget: N/A
- Project Priority: Standalone project
- Project Team: Digital Services, Public Services
Staff file storage and organization project
- Goal: Evaluate staff storage to improve file names and ease-of-use, delete and merge content as needed. Move some content onto staff intranet.
- Why: Streamline staff storage and make our staff files easier to use.
- Timeframe: 2016
- Budget: N/A
- Project Priority: Standalone project
- Project Team: Digital Services, Technical Services
Dispensers in Community expansion Project
- Goal: Rollout four more dispensers in 2015-2016.
- Why: We already have a goal of installing four more dispensers/book lockers in the community, and funding is in place.
- Timeframe: 2016-2017
- Budget: $50,000 a year in 2015 and 2016, funding through Friends
- Project Priority: Standalone project
- Project Team: Community Services, Digital Services
Service deployment in community evaluation and potential expansion
- Goal: Create contingency and expansion plan for community center computer centers.
- Why: Our current MOU with the county runs until 11/29/2017. We need to create a contingency plan to operate the community computer centers if the county doesn’t renew our contract. We should also discuss expanding in places the county won’t or can’t currently go.
- Timeframe: 2016-2017
- Budget: N/A
- Project Priority: Standalone project
- Project Team: Community Services, Digital Services, Administration
Potential Makerspace expansion
- Goal: Expand Make-It Lab based on findings of pilot project and evaluation phase.
- Why: Assuming the Make-It Lab is successful (it is so far), it will need a larger space with more activities and more workstations. It will also need some acoustic treatment for sound-proffing.
- Timeframe: 2016-2017
- Budget: TBD
- Project Priority: Connected with Main floor redesign
- Project Team: Digital Services, Public Services
Thin client Evaluation
- Goal: Evaluate thin clients for use on customer computers.
- Why: Thin clients are less expensive and easier for DS to manage. Evaluate the feasibility of a thin client system for both staff management and for customers.
- Timeframe: September 2016
- Budget: N/A
- Project Priority: Standalone project
- Project Team: Digital Services
Storage upgrade
- Goal: Evaluate Microsoft/Google Cloud storage/email needs and make recommendations.
- Why: We need to evaluate the feasibility of moving to a cloud-based storage and collaboration platform.
- Timeframe: 2016
- Budget: TBD
- Project Priority: Standalone project
- Project Team: Digital Services, yet-to-be created work team
2017
Meeting Room Technology Evaluation
- Goal: Evaluate meeting room A/V technology and make recommendations for changes and upgrades. Make sure to include options for music performances.
- Why: Planned evaluation to keep up-to-date with changing customer needs.
- Timeframe: 2017
- Budget: N/A
- Project Priority: Standalone project
- Project Team: Digital Services, Event Resources
Bandwidth evaluation
- Goal: Evaluate bandwidth needs, and suggest upgrades.
- Why: Provide the best web access possible to meet the needs of our customers.
- Timeframe: 2017
- Budget: N/A
- Project Priority: Standalone project
- Project Team: Digital Services
Security technology upgrade
- Goal: evaluate needs and make recommendations for a new security system that includes door access, cameras, storage, incident software, and panic buttons. Make recommendations for 2016 budget.
- Why: Planned evaluation to keep up-to-date with changing customer needs.
- Timeframe: 2017
- Budget: N/A
- Project Priority: Dependent on network upgrade
- Project Team: Security, Digital Services, Rob
2018
Bandwidth evaluation
- Goal: Evaluate bandwidth needs, and suggest upgrades.
- Why: Provide the best web access possible to meet the needs of our customers.
- Timeframe: 2018
- Budget: N/A
- Project Priority: Standalone project
- Project Team: Digital Services
2019
Bandwidth evaluation
- Goal: Evaluate bandwidth needs, and suggest upgrades.
- Why: Provide the best web access possible to meet the needs of our customers.
- Timeframe: 2019
- Budget: N/A
- Project Priority: Standalone project
- Project Team: Digital Services
2020
Bandwidth evaluation
- Goal: Evaluate bandwidth needs, and suggest upgrades.
- Why: Provide the best web access possible to meet the needs of our customers.
- Timeframe: 2020
- Budget: N/A
- Project Priority: Standalone project
- Project Team: Digital Services